STATUS UPDATE
The contractor is currently working on curb & gutter replacement and grading between Segoe Rd and Midvale Blvd. Asphalt paving and restoration of terraces has started. Paving is expected to be completed by August 24.
PROJECT DETAILS
Regent Street (Midvale Blvd – Whitney Way): Work is scheduled from May 21 to August 17. The project includes replacement of water main, sanitary sewer, storm sewer, pavement replacement, deteriorated curb and gutter replacement and some driveway apron replacement.
The street will be closed to through traffic. Local traffic will be maintained at all times. Bus traffic will be maintained westbound only from Eau Claire Ave to Regent St.
Additional information on the project can be found at: https://www.cityofmadison.com/business/PW/contracts/details.cfm?ContractNumber=6882
SECTION 1 (From Whitney Way to Eau Claire Ave)
Phase 1a (May 21st to August 17th)
Westbound lanes of Regent Street shall remain open to traffic between Whitney Way and Eau Claire Avenue. Right turns from southbound Eau Claire Ave to westbound Regent St shall be maintained. Eastbound traffic on Regent St may be restricted between Whitney Way and Eau Claire during Phase 1. Traffic lanes south of the median must be paved before moving to Phase 2.
Phase 1b (August 17th to August 31st)
Construction will take place north of the median on Regent St between Whitney Way and Eau Claire Avenue. In order to maintain bus traffic, westbound traffic will be switched over to south of the median between Eau Claire and Whitney Way. Eastbound traffic on Regent St may be restricted between Whitney Way and Eau Claire during Phase 2.
SECTION 2 (From Eau Claire Ave to Segoe Rd)
Phase 2 (May 21st to August 31st)
Regent St may be closed to thru traffic for the duration of construction in this section. Right turns from Eau Claire Ave to westbound Regent St shall be maintained with adequate room to accommodate Metro buses. Northbound and southbound traffic shall be maintained on Segoe Rd at all times. Adequate turning radii must be provided for Metro buses to make turns between Regent St and Segoe Rd prior to Phase 3.
SECTION 3 (From Segoe Rd to Midvale Blvd)
Phase 3 (June 27th to Aug 31st)
Regent St may be closed to thru traffic. Access must be maintained to the Associated Physicians driveway at 4410 Regent St. There will be times when the driveway will only be accessible by having vehicles drive eastbound from Price Pl on the north side of the Regent St median. Associated Physicians shall be notified 48 hours in advance of any access changes to their driveway. Northbound and southbound traffic shall be maintained on Segoe Rd.