Note: Whitney Way end date was revised to may 29 for Curb and gutter work.
Gammon Road (Seybold Rd – Schroeder Rd): Work is scheduled April 18 – April 29 for replacement of deteriorated curb and gutter and road castings. Pavement milling and resurfacing will follow in early to mid May.
The road will remain open to through traffic. However, lane closures will be required to complete the work. The resurfacing portion of the project will be competed at night from 8 pm to 7 am over one or two nights.
Additional information on the project can be found at: https://www.cityofmadison.com/business/PW/contracts/index.cfm. Contract numbers 6630, 6635.
Whitney Way (Hammersley Rd – Beltline Hwy & Mineral Point Rd – University Ave): Work is planned April 25 – May 29 with the installation of new storm sewer and replacement of curb and gutter. Pavement milling and resurfacing will start June 13 and last until July 20.
The road will remain open to through traffic at all times. However, lane closures will be required to complete the work.
Additional information on the project can be found at: https://www.cityofmadison.com/business/PW/contracts/index.cfm. Contract numbers 6638, 6635.
The proposed schedule for all streets: 2011ResurfacingConstructionSchedule.pdf
List of streets by groups and the contractors working on each group: streetgroups.pdf
For more information, visit the Street Resurfacing Program webpage.